Weeks After Latest Delay, Still No Word On Silver Line Opening | WAMU 88.5 - American University Radio

WAMU 88.5 : News

Weeks After Latest Delay, Still No Word On Silver Line Opening

Play associated audio
The McLean Metro station on the Silver Line will likely remain empty for the next several months.
Martin Di Caro/WAMU
The McLean Metro station on the Silver Line will likely remain empty for the next several months.

More than three weeks after the Metropolitan Washington Airports Authority (MWAA) rejected its lead contractor’s submission of “substantial completion” for Phase I of the Silver Line Metrorail project through Tysons Corner to Reston, officials on both sides of the dispute over the project’s construction problems remain mum as to when it will be ready.

MWAA is scheduled to hold its monthly board meeting this morning, but the project’s directors are expected to publicly reveal few details about ongoing negotiations with the construction giant Bechtel and its subcontractor Alstom Signaling, whose work on the Silver Line’s signaling system is at the center of the repeated delays. The Silver Line originally was supposed to open in January, meaning “substantial completion” needed to be attained in September.

On Feb. 24 MWAA directed Bechtel to provide a timetable for the necessary fixes, but on Tuesday officials seemed to be at odds over who is responsible for the next step in the approval process.

“MWAA has yet to specify what it believes needs to be done before we can re-submit the substantial completion package,” said Bechtel spokeswoman Michelle Michael.

As per Bechtel’s contract with MWAA, the contractor faces fines of $25,000 per day if the Silver Line is not finished and ready to be handed to Metro by April 9, but Michael said that date is subject to change because Bechtel was assigned work outside the scope of its original design.

The airports authority declined to respond directly to Bechtel’s statement.

“Since we announced our decision on Feb. 24 that [the contractors] had not yet met contractual requirements for substantial completion, we've been meeting more than once a day with [Bechtel] and Metro to address the outstanding issues,” said MWAA spokeswoman Marcia McAllister.

McAllister said Bechtel has not delivered a timetable for finishing Phase I of the Silver Line.

Since Metro will need up to three months to complete its own testing and training of its workforce, a late summer opening is growing more likely for the largest expansion of Metro’s rail system since its inception. When Bechtel next submits the $3 billion project as “substantially complete” another 15-day review period would begin before MWAA issues its ruling.

Metro repeatedly has declined to speculate about a possible start date for Silver Line service.

NPR

Buzz Bissinger: With Caitlyn Jenner, 'You Feel A Connection'

NPR's Melissa Block interviews Buzz Bissinger about his profile of Caitlyn Jenner in Vanity Fair and her gender transition. She is formerly known as Bruce, an Olympic gold medalist in the decathlon.
NPR

Grass Gourmands: A Herbivore Food Mystery On The African Savanna

A new study sheds light on a longstanding ecological question: How do so many species like impalas and elephants co-exist when they're all feeding on the same limited foods?
NPR

House Panel Questions Air Bag Manufacturer About Chemical Explosive It Uses

Lawmakers wanted to know more about the recall of some 34 million vehicles that have potentially defective air bags made by the Takata Corporation. Congress wants to know what caused the problem.
NPR

Experts Debate: Will Computers Edge People Out Of Entire Careers?

Machines have been taking jobs forever. Computers and software are doing things people were paid to do. They are booking airplane flights. Filing our taxes. And they are getting better all the time.

Leave a Comment

Help keep the conversation civil. Please refer to our Terms of Use and Code of Conduct before posting your comments.