Metro's Silver Line Will Start Running... Well, It's Not Yet Clear When

The agency constructing the first phase of the Silver Line rail project to Tysons Corner and Reston remains unable to estimate a date for the start of passenger service, three and a half months before Metro hopes to begin collecting fare revenue.

Officials at the Metropolitan Washington Airports Authority (MWAA) on Wednesday said Phase 1 of the Silver Line will cost close to $3 billion and will likely be handed over to WMATA for the completion of safety testing and workforce training sometime in November, at which point the transit authority will have up to 90 days to finish its work before opening the rail extension with the blessing of the Federal Transit Administration.

But given the enormity of the project and the amount of work that remains, MWAA is reluctant to name precise dates that might raise the expectations of an eager public.

“At this point in time we’re not yet prepared to even name a substantial completion date for the project,” said Pat Nowakowski, the Silver Line's executive director at MWAA. “You have to understand, the 'up-to-90-days' was just in a cooperative agreement. There is no contract that binds them to that amount of days. [Metro] need to do their tests and their familiarization and whatever it takes, it takes.”

Metro would like to open the Silver Line (Phase 1 will run from the East Falls Church area westward with four stations in Tysons Corner and one at the eastern edge of Reston at Wiehle Avenue) as soon as possible. The transit authority in its budget is anticipating monthly passenger fare revenues of approximately $1.5 million. If the trains aren’t running as of January 1, Metro will still have to cover operating expenses for its new workforce of train operators and transit police.

At MWAA’s monthly board meeting, CEO Jack Potter said some testing required by Metro is being completed now while the project is still in the hands of the airports authority, potentially shortening the 90-day window. Nowakowski said Metro can only accomplish so much while the Silver Line is being finished.

“They’ve got a whole workforce that they’ve got to familiarize with this line. It’s a new addition. They need to do drills with first responders… and they can’t do that while we are out there building. They need to do that with their people, without us,” he said.

Engineers have not encountered any significant safety issues or design flaws in these final months before the Silver Line carries its first passengers, but Nowakowski said small blips are frequently encountered, as you would expect with such a large project.

“We’re anxious as well and we are just not at this point in time able to give people a date yet,” he said.

NPR

Small South Carolina Newspaper Takes Home Top Pulitzer Prize

The winners of this year's Pulitzer Prizes in journalism, fiction, poetry, drama, music, biography, history and nonfiction were announced Monday at Columbia University in New York.
NPR

When Danish Cows See Fresh Spring Pasture, They Jump For Joy

Thousands of spectators gather every April to see ecstatic cows return to fields on organic farms around Denmark. The organic industry says the event has helped fuel demand for organic foods.
WAMU 88.5

Hello, Goodbye: Pair Of Virginia Delegates Depart After Short Careers In Richmond

Some members of the Virginia's General Assembly are throwing in the towel, deciding against seeking reelection. — and some of them haven't been around for very long.
NPR

Norway Becoming First Country To Eliminate FM Radio

The switch from analog to digital radio offers more channels at a fraction of the cost, the government says.

Leave a Comment

Help keep the conversation civil. Please refer to our Terms of Use and Code of Conduct before posting your comments.