Metro Can't Walk Away From Silver Spring Transit Center, Says Montgomery Co. | WAMU 88.5 - American University Radio

WAMU 88.5 : News

Filed Under:

Metro Can't Walk Away From Silver Spring Transit Center, Says Montgomery Co.

Play associated audio
Metro says construction and design of the Silver Spring Transit Center make it too expensive to maintain.
Jared Angle
Metro says construction and design of the Silver Spring Transit Center make it too expensive to maintain.

Metro is obligated to operate the structurally flawed Silver Spring Transit Center when the facility is finally repaired and open for business, Montgomery County officials said during a hearing on Wednesday.

In response to the transit authority's move to inform the county it will not accept the three-level bus and train hub "even if repaired to permit regular service" because "it would unnecessarily place an inordinate maintenance burden onto WMATA," the Montgomery County Council signaled it has no intention of letting Metro quit a project that is two years behind schedule and millions over budget.

"Metro has been a partner in this from day one," said County Councilman Roger Berliner. "And now they can't simply say, sorry, we're done. No, they are not done. We are working on it. We are going to deliver a state of the art facility. There will not be any basis for them to walk."

The two sides are talking, according to David Dise, the county's director of general services.

"We have met with them and we believe have initiated discussions on their position," Dise said. "We believe this is a posture on their part. We believe there is still opportunity to negotiate their position."

In an April 30 letter, the Montgomery County Council notified WMATA it intends to hand the transit agency a "fully functional facility. The County continues to honor its obligations... and it expects WMATA to also honor its obligations."

During the forty minute hearing on Wednesday councilmembers grilled members of County Executive Ike Leggett's staff about negotiations with Metro. But Councilman Phil Andrews asked the question just about everybody would like an answer to.

"What is a realistic schedule for when it will be open?"

"I don't know," Dise said. "What I can say is that we should have a remediation plan in place in a month's time."

The fate of the transit center was thrown into turmoil after a county report in March found excessive cracking in concrete, missing cables, inadequate reinforcing steel, and concrete of insufficient strength and thickness.

The report provoked a response from the general contractor, Rockville-based Foulger-Pratt, which said it simply followed the county's own design plans when pouring concrete at the transit hub.

Metro's move to threaten to back out of the project added another layer of troubles, potentially leaving the county with a concrete edifice and no one to operate it. "The county has never run a transit center like this," Councilman Berliner said.

No Metro officials spoke at the hearing, and it did not even seem that any where present for it. But in a statement on Wednesday, Metro spokesman Dan Stessel said the transit authority's position has not changed.

"We continue to have an open dialogue with the County, and we are prepared to listen to any remediation plan that they may develop. We are willing to operate Metrobus service out of the facility," Stessel said.

Montgomery County Letter To WMATA Regarding SSTC by WAMU885news

NPR

Speed Dating For Seniors Who Aren't Interested In Slowing Down

A new film follows daters ages 70 to 90 looking for love in five-minute intervals. "Speed dating for seniors" may sound funny, but The Age of Love is really about our lifelong need for intimacy.
NPR

Eat Your Veggies! Even The Ones From Fukushima

Foods from Fukushima, Japan, are back to pre-accident levels of radiation but people still aren't eating them. One way to ease concerns: a chemical that blocks radioactive cesium from entering plants.
WAMU 88.5

Fairfax County Supervisors Approve Pay Bump For Themselves

Members of the Fairfax County Board of Supervisors are about to start earning more money, as the current members have approved a measure that will raise salaries for the next board.
NPR

Apple To Replace AT&T In Dow Jones Industrial Average

The tech giant will replace the telecoms giant after the close of trading March 18. The change, effective March 19, was prompted by stock splits announced by Apple and Visa.

Leave a Comment

Help keep the conversation civil. Please refer to our Terms of Use and Code of Conduct before posting your comments.